The municipality of Wenzenbach intends the general renovation of the middle school Wenzenbach at the location Roither Weg 15 in 93173 Wenzenbach. According to the current state of the preliminary planning, a merger of the mentioned middle school with the primary school Wenzenbach is to take place in the course of the renovation, which is currently located at Pestalozzistraße 15, also in Wenzenbach. It is planned to adapt the existing school complex to the future space requirements of a joint primary and secondary school through partial demolitions and new buildings and to create a modern learning landscape. According to school demand planning, the municipality of Wenzenbach is entitled to a 2-field sports hall when combining primary and secondary school into one school complex. This is to be rebuilt in the course of the construction measures of the school. The planning services structural design incl. special services are put out to tender. See II.2.4 for the rest.
The municipality of Wenzenbach intends the general renovation of the middle school Wenzenbach at the location Roither Weg 15 in 93173 Wenzenbach. According to the current state of the preliminary planning, a merger of the mentioned middle school with the primary school Wenzenbach is to take place in the course of the renovation, which is currently located at Pestalozzistraße 15, also in Wenzenbach. It is planned to adapt the existing school complex to the future space requirements of a joint primary and secondary school through partial demolitions and new buildings and to create a modern learning landscape.
According to school demand planning, the municipality of Wenzenbach is entitled to a 2-field sports hall when combining primary and secondary school into one school complex. This is to be rebuilt in the course of the construction measures of the school. It must be clarified whether the municipality sees the need for a 3-field hall and implements it without the funding for the third hall field. The option of extending the new construction of a 2-field hall by another field is to be provided.
The existing 2-field sports hall at Roither Weg 15 is not part of the further planning.
In coordination with all other specialist planners involved, a structural plan must be drawn up both for the planned renovation measures and for the new construction sections. Collisions with the building services trades must be clarified before construction begins, so that they will not lead to delays in the construction process. Furthermore, the work on load-bearing components must be monitored and this monitoring must be documented.
We are therefore looking for a planning office for the structural design service profile in accordance with § 51 HOAI, which develops a renovation concept in close coordination with other specialist planners involved, prepares its implementation and monitors it during construction.
The work phases 1 to 6 AND the engineering technical control as well as numerous special services designed as options are to be commissioned.
The planning is to take place immediately after the commissioning (approx. March 2023), funding application will be submitted in 2023.
The construction project is taking place parallel to the ongoing school operations.
It is to be expected with construction phase formation, to create this sensibly is part of the planning task.
Start of construction planned: quarter 01/2024
Completion: quarter 02/2029
Start of use: Start of school year 2029/2030, i.e. 01.09.2029.