The technical specifications are given in the main project no. 002-21 of Tuulekaru OÜ and its annexes.
The project documentation can be found at: https://tartulv-my.sharepoint.com/:f:/g/personal/mihkel_vijar_tartu_ee/EvwpWb7iyq1Dqx6gmb18zzIBPVpQ4CkMzvf20MjgqF7I4g?e=LaBjgM
The working land is divided into four stages:
The works of stages I and II are 100% financed by the Tartu City Government and AS Tartu Veevärk for the construction of water and wastewater sewerage pipelines (water pipeline nodes between V-1 and V-24 and sewage sewerage wells between K-1 and K-8).
The works in stages III and IV are financed by Tartu City Government and Tartu Rural Municipality Government to the extent of 50% each.
The contract for the construction of pipelines is entered into by AS Tartu Veevärk.
The technical specifications are given in the main project no. 002-21 of Tuulekaru OÜ and its annexes.
The project documentation can be found at: https://tartulv-my.sharepoint.com/:f:/g/personal/mihkel_vijar_tartu_ee/EvwpWb7iyq1Dqx6gmb18zzIBPVpQ4CkMzvf20MjgqF7I4g?e=LaBjgM
The working land is divided into four stages:
The works of stages I and II are 100% financed by the Tartu City Government and AS Tartu Veevärk for the construction of water and wastewater sewerage pipelines (water pipeline nodes between V-1 and V-24 and sewage sewerage wells between K-1 and K-8).
The works in stages III and IV are financed by Tartu City Government and Tartu Rural Municipality Government to the extent of 50% each.
The contract for the construction of pipelines is entered into by AS Tartu Veevärk.