1. The subject of the contract is the supply of electricity in the period of:
Part 1 of the order - 01.01.2024r. to 31.12.2024r. – estimated volume 6 090.36 MWh
Part 2 orders - 01.01.2025r. to 31.12.2025r. - estimated volume 6 090.36 MWh
2. The forecast electricity consumption is indicative and may differ from the amount of energy actually consumed during the term of the contract. Reducing or increasing the amount of electricity does not entail any consequences for the ordering party, except for the need to pay for the amount of energy actually consumed.
3. Applicable settlement periods: Tariff group Bx, C2x – 1 month; C1x – 2 months.
4. Distribution services are/will be provided on the basis of separate agreements concluded between the contracting authority and the DSO.
5. The condition for starting electricity supplies within the indicated time limit (for individual consumption points) is a positive completion of the procedure of changing the supplier.
Electricity supply in 20241. Number of metering systems accounting for consumed electricity 31 pcs.
2. A detailed description of the pre-emptive points (PPE) of the Contracting Party included in Annex No 1a to the SWZ.
3. Estimated electricity consumption during the term of the contract – 6 090.36 MWh.
Consumption data is indicative. In the case of launching a RES installation, as described in point 5 below, the amount of purchased energy during the term of the contract may be reduced by approx. 115 MWh. Installation of PV installations depends on obtaining external funding by the contracting authority.
4. Deliveries will take place from 01.01.2024. to 31.12.2024r.
5. In the second half of 2024, the contracting authority plans to carry out investments consisting in the assembly of 4 PV installations (detailed data in Annex 1a to the SWZ) and obtain the status of a Producer. The total estimated amount of energy generated in the installations is 251 MWh per year. The contracting authority estimates that almost all of the energy generated in RES installations will be used on an ongoing basis for the needs of facilities (with the exception of the PPE 590243895024506091 facility, where the contracting authority provides for energy resale at the level of 0.5 MWh per year). However, due to the applicable regulations, the contracting authority provides for the conclusion of a contract for balancing and repurchase of energy generated in the PV installation with the contractor (based on the template used by the contractor), whose offer will be selected. The contracting authority shall inform the contractor about the planned connection of the installation to the public network immediately after submitting the application for its connection.
6. Current electricity supply contracts shall expire or terminate with effect from the day before the planned start date of supply (column 'Delivery period'). The obligation to terminate the contracts lies with the ordering party.
7. Quality standards
1) The subject of the order is the supply of electricity with certain quality standards in accordance with applicable regulations.
2) Electricity quality standards are described in the Pe Act and in the Regulation of the Minister of Economy of 4.05.2007. on the detailed conditions for the operation of the power system (Journal of Laws of 2007 No. 93, item 623 with późń.zm.) amended by the Regulation of the Minister of Climate and Environment of 27.09.2022 amending the regulation on detailed conditions for the operation of the power system (Journal of Laws of 2022, item 2007). The rules for shaping and calculating tariffs and settlements in electricity trading are specified in the Regulation of the Minister of Climate and Environment of 29 November 2022 (Journal of Laws of 2022, item 2505 with późń.zm.).
8. Measurement systems with tariff group B are tailored to the seller's change procedure.
9. The Contractor, based on the Power of Attorney granted, will be obliged to submit the contract on its own behalf and the contracting authority to the relevant DSO in accordance with applicable regulations and to represent the contracting authority before the DSO in the process of changing the seller.
10. The contracting authority reserves the right to use Article 139(1) of the PPL, i.e. the possibility of first examining and evaluating bids, and then subjective qualification of the contractor whose bid was rated the highest, in terms of the lack of grounds for exclusion and meeting the conditions for participation in the procedure.
11. The Ordering Party does not require the provision of a performance bond.
12. The Ordering Party shall request the lodging of a security deposit. In the case of submitting an offer for Part 1 of the order: PLN 60,000.00.
13. The Ordering Party acts through a Plenipotentiary: Pomorska Grupa Konsultingowa S.A., Unii Lubelskiej 4c, 85-059 Bydgoszcz.
Electricity supply in 20251. Number of metering systems accounting for consumed electricity 31 pcs.
2. A detailed description of the pre-emptive points (PPE) of the Contracting Party included in Annex No 1b to the SWZ.
3. Estimated electricity consumption during the term of the contract – 6 090.36 MWh.
Consumption data is indicative. If the RES installation is launched in 2024, the amount of energy purchased during the term of the contract may be reduced by approx. 251 MWh.
4. Deliveries will take place from 01.01.2025. to 31.12.2025r.
5. In 2024, the Contracting Authority provides for the installation and commissioning of PV installations in the locations indicated in Annex 1b to the SWZ and obtaining the status of a Producer. Since the investment depends on obtaining external funding, the contracting authority allows that if the subsidy is not obtained in 2024, the construction of the PV installation may take place in 2025. The contracting authority estimates that almost all of the energy generated in RES installations will be used on an ongoing basis for the needs of facilities (with the exception of the PPE 590243895024506091 facility, where the contracting authority provides for energy resale at the level of 0.5 MWh per year). However, due to the applicable regulations, the contracting authority provides for the conclusion of a contract for balancing and repurchase of energy generated in the PV installation with the contractor (based on the template used by the contractor), whose offer will be selected. The contracting authority shall inform the contractor about the planned connection of the installation to the public network immediately after submitting the application for its connection.
6. Current electricity supply contracts shall expire or terminate with effect from the day before the planned start date of supply (column 'Delivery period'). The obligation to terminate the contracts lies with the ordering party.
7. Quality standards
1) The subject of the order is the supply of electricity with certain quality standards in accordance with applicable regulations.
2) Electricity quality standards are described in the Pe Act and in the Regulation of the Minister of Economy of 4.05.2007. on the detailed conditions for the operation of the power system (Journal of Laws of 2007 No. 93, item 623 with późń.zm.) amended by the Regulation of the Minister of Climate and Environment of 27.09.2022 amending the regulation on detailed conditions for the operation of the power system (Journal of Laws of 2022, item 2007). The rules for shaping and calculating tariffs and settlements in electricity trading are specified in the Regulation of the Minister of Climate and Environment of 29 November 2022 (Journal of Laws of 2022, item 2505 with późń.zm.).
8. Measurement systems with tariff group B are tailored to the seller's change procedure.
9. The Contractor, based on the Power of Attorney granted, will be obliged to submit the contract on its own behalf and the contracting authority to the relevant DSO in accordance with applicable regulations and to represent the contracting authority before the DSO in the process of changing the seller.
10. The contracting authority reserves the right to use Article 139(1) of the PPL, i.e. the possibility of first examining and evaluating bids, and then subjective qualification of the contractor whose bid was rated the highest, in terms of the lack of grounds for exclusion and meeting the conditions for participation in the procedure.
11. The Ordering Party does not require the provision of a performance bond.
12. The Ordering Party shall request the lodging of a security deposit. In the case of submitting an offer for Part 2 of the order: PLN 60,000.00.
13. The Ordering Party acts through a Plenipotentiary: Pomorska Grupa Konsultingowa S.A., Unii Lubelskiej 4c, 85-059 Bydgoszcz.