Replacement new building Pestalozzi school construction phase 1
approx. 5,900 m³ excavated earth
supply and install approx. 5,900 m³ of soil
Dig and refill approx. 250 m³ pipe trench
lay approx. 650 m drain pipes
produce approx. 3,400 m³ of façade scaffolding
ca. 2.300 m² Stahlbetonbodenplatte
produce approx. 2,800 m² of reinforced concrete walls
produce approx. 4,750 m² reinforced concrete ceiling
approx. 2,300 m² of interior walls made of sand-lime brick