VE5272 Bridge over rivers (AFG) Waltendorf
The structure is being erected to ensure the accessibility of the newly emerging island south of the village of Waltendorf between the Danube and the Waltendorf watercourse and crosses the floodplain. The production of the watercourse will take place on an ongoing basis, starting from 03/2024. The dike relocation in Waltendorf will take place before the start of the bridge construction work. Thus, the bridge construction site is not located in the flood-protected area. The structure is built in a sloped excavation pit. A small dam will be poured around as flood protection and a narrow wall will be sunk with integration into the Tertiary.
- Earthworks approx. 12,500 m3 (5,500 m3 earthworks, 7,000 m3 excavation)
- Stahlbetonarbeiten ca. 300 m3
- Schmalwandarbeiten ca. 3.700 m2
- Spundwandarbeiten ca. 50 m2
- Steelwork railing 70 m
- Wegebauarbeiten ca. 165 m2
- Wasserhaltungsanlage