Delivery, installation and commissioning of a new geo-redundant interconnected control system at two locations
and reconnection of previous control technology during operation.
Delivery, installation and commissioning of a new multi-redundant composite control system
geo-redundant at two locations. The commissioning will be carried out as a conversion of the existing control system of the
manufacturer Siemens (Spectrum Power 4) on the new control technology during operation with subsequent
Data point test. The scope of supply also includes the renewal of six telecontrol nodes with the implementation of
IEC 60870-5-101 auf IEC 60870-5-104.
Prior to the start of the construction project, the contractor develops the following from the specifications in the detailed planning phase:
and the associated annexes. The Client assures the necessary support for this. After
Once the specifications have been approved by the Client, the main order is activated and the building permit is granted.
The order is scheduled to be executed approximately from April 2024 to December 2025.