GWG Ingolstadt is carrying out the construction of a new residential complex with a day care center on Stargarder Strasse, consisting of 5 houses, including 2 high-rise buildings with 12 and 18 upper floors respectively, and a large underground garage. The master builder work has been in progress since August the year before last, and the execution of facade and finishing works will begin in 2022.
Dimensions:
Number of apartments 161 (plus day care with 4 groups)
BRI total approx. 75,000 m3 of which underground car park approx. 11,000 m3
GFA total approx. 24,000 m2, of which underground parking approx. 3,500m2
Building heights of approx. 13 m to 55 m above OK grounds (ancillary facilities up to approx. 4 m)
The following services are to be offered for the construction project:
Production, supply and installation of grating covers made of pressed gratings of different dimensions on light and ventilation shafts, partly with UK made of steel profiles, all parts hot-dip galvanized, total approx. 125 m²
Production, delivery and installation of 4 grating stairs with flat steel cheeks made of hot-dip galvanized steel, width 1.00 – 1.50m, 2 x with 5 pcs., approx. 17 / 29, 2 x with 10 pcs., 18.5 / 27
Manufacture Delivery and assembly of various doors B 0.90 – 1.25m, H up to 2.50m, installation in passages / escape routes / TG, with grating or perforated sheet metal filling and panels, partly UK made of profile steel, all parts hot-dip galvanized, a total of 7 pieces
Inspection flaps made of stainless steel, for installation in brick curtain wall, 0.32 x 0.32m, total 20 pieces
Delivery / installation smoke protection sliding door with slip door in the TG, tight-closing, powder-coated, with steel substructure for opening 5.25 x 3.00m, 1 piece