Klinikum Lippe Detmold, construction painting technology.
The construction project includes the new building component C to 2nd floor following an existing building. For the
Transitions will require reconstruction work in individual areas and floors. There is an expansion of the
1.OP cluster, the 2nd OP cluster is initially only created as a shell.
painting work
10,651 m² wall coatings
4.540 m² Deckenanstrich
215 m² coating of stairs
850 m² painted steel frames
340 m² painted sheet steel doors, sheet steel flaps
140 m² thermal insulation composite system
550 m² Temporary closing façade
The performance requirements are shown in their entirety from the procurement documents.