- Schutznetze ca. 355 m²
- Demolition of plumbing components: gutter, eaves strips, ventilation grilles etc. approx. 60 m, demolition of downpipes approx. 20 m
- Demolition of lightning protection system approx. 110 m
- Demolition of roof structure approx. 385 m², consisting of:
Bituminous waterproofing with primer, roof formwork, squared timber layer, timber beam layer (approx. 15 m³), mineral wool roof insulation (KMF),
Carrying and ceiling cladding made of wooden panels.
- Dismantling luminaires (approx. 25 pieces) and electrical cables
- Disposal of mineral wool "old", bitumen, waste wood (category III and IV), titanium zinc plumbing components
- Schutznetze ca. 355 m²
- Demolition of plumbing components: gutter, eaves strips, ventilation grilles etc. approx. 60 m, demolition of downpipes approx. 20 m
- Demolition of lightning protection system approx. 110 m
- Demolition of roof structure approx. 385 m², consisting of:
Bituminous waterproofing with primer, roof formwork, squared timber layer, timber beam layer (approx. 15 m³), mineral wool roof insulation (KMF), carrying and
Ceiling cladding made of wooden panels.
- Dismantling luminaires (approx. 25 pieces) and electrical cables
- Disposal of mineral wool "old", bitumen, waste wood (category III and IV), titanium zinc plumbing components