The science city of Darmstadt is planning the new construction of the Heinrich Hoffmann School and kindergarten in Darmstadt, between Lindenhofstraße and Woogsplatz.
It is an ensemble consisting of three individual buildings: a school building, a daycare center and a single-field sports hall in the inner-city environment or city center.
The school and daycare center are completely carried out as reinforced concrete skeleton construction. The sports hall is built as a hybrid building, i.e. the garden level in concrete and the ground floor in timber construction.
On the performance of this call for tenders:
The subject matter of the service is:
- 559.84 m2 bio-polyurethane flooring
- 223.78 m2 baffle wall substructure
- 261.35 m2 of wooden interior cladding
- Sporthallentüren
- Floating gate sports hall
The planned execution dates are:
Sports flooring:
Assembly planning: 10 days
From 08.11.23 to Wed 22.11.23
Sampling: 1 day
Fri 17.11.23 to Mon 20.11.23
Workshop assembly: 5 days
From 11/22/23 to 11/29/23
Construction site installation of sports floor substructure: 5 days
Wed 29.11.23 to Wed 06.12.23
Construction site installation pavement: 5 days
Wed 11/29/23 to Wed 12/13/23
Floor markings incl. drying: 10 days
Wed 20.12.23 to Wed 03.01.24
Baffle:
Assembly planning: 15 days
Wed 04.10.23 to Wed 25.10.23
Sampling: 1 day
Fri 13.10.23 to Mon 16.10.23
Workshop assembly: 15 days
Wed 10/25/23 to Wed 11/15/23
Construction site installation, gates, baffle walls, etc.: 15 days
Wed 15.11.23 to Wed 06.12.23
Construction site installation baffle wall plinth: 5 days
Wed 13.12.23 to Wed 20.12.23
- Sports floor and baffle wall