A new incineration plant will be constructed next to the existing incineration plant whilst the existing incineration plant is in operation. The new building will include an administration wing, a waste hall, and a process hall. The existing building will be used for storage and as a workshop.
This is a prequalification. The contracting authority will choose 3 tenderers.
A new incineration plant will be constructed next to the existing incineration plant whilst the existing incineration plant is in operation. The new buildings will include an administration wing, a waste hall, and a process hall. The existing building will be used for storage and as a workshop.
The waste hall will have a supporting system, walls of concrete that are partially cast on site, and partially prefabricated concrete elements as well as a roof construction of prefabricated concrete elements.
The process hall with the incineration plant will have a supporting system of steel or prefabricated concrete, walls of concrete case on site, partially prefabricated concrete elements, as well as partially sandwich panels.
The administration wing will have 6 floors with a supporting system of prefabricated concrete elements, and will include technical rooms in the basement, on the ground floor, and 5th floor. The stairway and person lift will go from the ground floor to the 5th floor. The rooms in the office areas will be separated by wall of steel pillars and mineral wool covered with plasterboard.
The buildings' total area of use will be approx. 2600 m2.
Complete details will be available when the contracting authority has chosen 3 tenderers. These three tenderers will be able to submit a tender.
This is a prequalification. The contracting authority will choose 3 tenderers.