Track construction works | Tenderlake

Track construction works

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
22 June 2023
Closing Date:
20 July 2023
Location(s):
DE123 Karlsruhe, Landkreis (DE Germany/DEUTSCHLAND)
Description:
A 30-23 Schwaigern-Leingarten

Traffic systems and engineering structures

The AVG is planning the duplication of the Heilbronn - Eppingen line (AVG line 94950) between the Leingarten West station and the Schwaigern station over a length of approx. 3.2 km. The current single-track section is to be operated on two tracks in the future. In addition to the necessary additional track, existing switch connections are to be supplemented or new transfer connections are to be created. For this purpose, the conversion of the 6 existing points is planned (5 as a new building, one as a renewal).

In the course of the new construction of the second track, the superstructure of the existing track must also be adapted to the new drainage situation. The existing cable duct must be replaced along the entire route. Furthermore, in the course of the double-track expansion, the extension of the track body will also be necessary, including the adaptation or renewal of four culvert structures along the line.

In addition, for the Heilbronn - Eppingen direction at the Schwaigern-Ost HP (TSWO), the construction of a new platform on the new track is required. The platform is designed as a prefabricated platform with deep foundations. Access to the platform is provided by means of a ramp system. Furthermore, the measure includes the adaptation of two level crossings (railway km 127.3+21 and railway km 128.2+16) to the new track geometry, the extension of the pedestrian underpass (EÜ at railway km 129.062) west of the "Schwaigern-Ost" stop and the construction of a new noise barrier in the area of the existing platform at the Schwaigern-Ost HP.

Track construction:

Clearing the building site approx. 44,000 m²

Removing and temporarily storing the track approx. 3,250 m

Dismantling and disposing of concrete sleepers approx. 5,000 pcs

Removing track ballast, screening, cleaning and temporary storage approx. 6,500 m³

Removal, intermediate storage and disposal of track ballast approx. 6,700 m³

Remove turnouts approx. 2 hours

Dismantle and dispose of the existing cable trough including shafts approx. 3,200 m

Removal of topsoil and temporary storage approx. 3,000 m³

Loosening, temporarily storing and disposing of soil approx. 17,000 m³

Soil improvement d=40cm by means of lime-cement mixture approx. 38,500 m²

Geotextile supply and installation (200 g) approx. 38,500 m²

Construct track (existing rails, sleepers on site) approx. 2,450 m

Manufacture of track (delivery of rails + sleepers on site) approx. 3,700 m

Install turnouts (delivery of turnouts on site) approx. 6 pcs

Delivery and installation of track ballast approx. 16,000 t

Installing intermediate track ballast approx. 12,000 t

Production of edge paths approx. 6,000 m

Production of ballast bracket with railing approx. 700 m

Establish deep drainage approx. 3,700 m

Entwässerungsschächte DN 600 ca. 65 St

Entwässerungsschächte DN 1000 ca. 10 St

Adaptation of pipe outlets approx. 3 pcs

Adaptation of culvert structure approx. 1 hour

Adaptation EÜ approx. 1 hour

Production of infiltration trough approx. 1 pc

Supplying and installing cable duct size III approx. 3,200 m

Cable duct size IV deliver and install approx. 50 pcs

Civil engineering level crossings:

Dismantling of level crossings approx. 2 hours

Break up and dispose of asphalt pavement, up to 20 cm approx. 870 m²

Supply and install track slab approx. 110 m²

Making asphalt roadway approx. 970 m²

Laying foundations for level crossing, approx. 24 pcs

Supplying and installing empty conduits DN 110 approx. 530 m

Deliver and install cable ducts approx. 8 pcs

Extension breakpoint:

Micropile Ø 100 mm, L = approx. 12 m, inclined, manufacture approx. 1,375 m

Header beam made of bew. Produce concrete including formwork approx. 40 m³

Steel structure access ramp approx. 23 t

Precast concrete elements Access ramp approx. 50 m³

Ramp flooring incl. waterproofing and gravel bed approx. 135 m²

Deliver and install prefabricated platform nominal height 55 cm above SE approx. 340 m²

Construct empty conduit line in the platform incl. shafts approx. 120 m

Deliver and assemble a weather shelter approx. 1 pc

Deliver and install filler bar railings approx. 360 m

Deliver and assemble handrail approx. 240 m

New construction of noise barrier:

Foundation Supplying and installing tubular steel piles Ø 610, L 4 to 6 m approx. 415 m

LSW-Stahlpfosten, HEM 160 ca. 53 t

LSW plinth as precast concrete element, d = min.12.5cm approx. 255 m²

LSW wall element made of light metal incl. corrosion protection approx. 1,030 m²

Rescue door in LSW, wxh=1,60x2,20m approx. 1 pc

Access road for rescue door with access stairs and platform made of steel approx. 1 hour

Download full details as .pdf
The Buyer:
Albtal-Verkehrs-Gesellschaft mbH
CPV Code(s):
45221250 - Underground work other than tunnels, shafts and subways
45223210 - Structural steelworks
45234116 - Track construction works