Building demolition and wrecking work and earthmoving work | Tenderlake

Building demolition and wrecking work and earthmoving work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
02 May 2023
Closing Date:
18 May 2023
Location(s):
FRI21 Corrèze (FR FRANCE)
Description:
REMOVAL OF THE WINCHES OF THE FLOOD EVACUATORS RIGHT BANK

The object of the Contract is to:

- Carry out execution studies

- Write risk analyses and operating procedures prior to the work

- draft and file ASBESTOS removal plans

- dismantle the 3 winches of the EVCRD (winches + tree line) (Presence of ASBESTOS AND LEAD)

- demolish and level the concrete studs that are the supports of the winches

- dismantle the Wales chains that connect the valves to the shaft line

- dismantle an ole-hydraulic power plant and its network of rigid pipes (ASBESTOS AND LEAD)

- Dismantle ladder-type accesses with crinolines + bodyguards

- evacuate all dismantled equipment in approved channels (monitoring of hazardous asbestos/lead waste)

- provide all handling equipment / access to carry out the work

- Provide reports, minutes, administrative and technical documents of the work in an end-of-case file

The work will be carried out on the safety organs of a hydroelectric dam and in 2 phases:

- Execution studies

- Installation and withdrawal of construction site on the crown of the dam (altitude 420mNGF)

- Demolition/dismantling of the winches of the Right Bank Flood Evacuators (EVCRD). The equipment is positioned on a concrete platform at a height of 8m.

- Disposal of dismantled equipment in approved channels (monitoring of hazardous asbestos/lead waste)

- Participation in site monitoring meetings

- Drafting of the End of Business Brief.

1st phase of work in Q1/2024 on the Right Bank Flood Evacuator valve n°3 (EVCRD3)

- dismantle the winch (winches + shaft line) (Presence of ASBESTOS AND LEAD)

- demolish and level the concrete studs that are the supports of the winches

- dismantle the Wales chains that connect the valves to the shaft line

- evacuate all dismantled equipment in approved channels

- provide all handling equipment / access to carry out the work

2nd phase of work in July/August/Sept 2025 on EVCRD2 and EVCRD1

- dismantle winches (winches + tree line) (Presence of ASBESTOS AND LEAD)

- demolish and level the concrete studs that are the supports of the winches

- dismantle the Wales chains that connect the valves to the shaft line

- dismantle an ole-hydraulic power plant and its network of rigid pipes (ASBESTOS AND LEAD)

- Dismantle ladder-type accesses with crinolines + bodyguards

- evacuate all dismantled equipment in approved channels

- provide all handling equipment / access to carry out the work

Download full details as .pdf
The Buyer:
SHEM ENGIE
CPV Code(s):
45110000 - Building demolition and wrecking work and earthmoving work