Earthwork and structural work.
All ca information:
- 5 500 m 3rd Excavation;
- 4,000 m 3rd Replacement;
- 1 250 m vibrating pillar;
- 220 m 3rd STB foundations;
- 510 m 3rd STB floor slabs;
- 715 m 3rd STB walls / supports / lintels;
- 650 m 3rd STB blankets;
- 620 m STB-FT ceiling edges;
- 18 STB-FT staircases;
- 320 t of structural steel;
- 3 800 m 2nd Insulation;
- 1 450 m 2nd Fresh concrete composite films.