The Fritz Ulrich School, a 3-class community school with approx. 450 pupils, will be expanded for full-day operation, expanded barrier-free and renovated.
The school consists of two building blocks from 1965, offset by 1.86 m from each other, which are connected by three stairwells in split-level construction, and a further one-storey, raised structure built in 2008 with connection via 2 bridges.
As an extension, the inner courtyards between the stairwells are covered and used as areas for all-day use (cafeteria / theater workshop).
The building blocks are accessible with new galleries in the atria and a new elevator system.
The measure includes the constructive and safety-related fire protection renovation. The construction work will be carried out in three phases during operation from summer 2020 to 2022.
- Building data: GFA approx. 7 050 m
- BRI approx. 29,000 m³.
Tile and plate work:
- Tile coverings WC's / sanitary rooms on floor and wall with sealing approx. 280 m
- Kitchen tiles R10 / R11 on the floor and wall with waterproofing W3-1 approx. 420 m
- Floating cement screed approx. 140 m
- Cast stone covering approx. 220 m