L 167, OD Neuruppin, ABS 030, road construction
The basic expansion of the L 167 in the OD Neuruppin begins in the north in the Wittstocker Allee (para. 030, Str.km 4.569) and ends in the south in the street "Seedamm" (para. 030, Str.km 3.343).
Straßenbauleistungen
approx. 6200 m3 of soil, loading, recycling
approx. 5670 m3 floor replacement, thickness 30 and 20 cm
approx. 26750 m2 of grade
approx. 450 m3 of topsoil supply and cover
approx. 4000 m2 of lawn seeding
absorb approx. 3700 m3 of layers without binders,
approx. 3930 m of curbs
approx. 21400 m2 of natural stone paving (KP, GP, FP, Mo)
Approx. 1000 m2 of concrete slab covering
Approx. 500 m2 of slab covering made of natural stone
approx. 750 m2 of concrete block pavement
Produce approx. 9200 m3 of ballast base courses (roadway and ancillary areas)
approx. 4550 m2 of asphalt pavements
Produce approx. 13000 m2 of asphalt base course
Produce approx. 13000 m2 of asphalt binder layer
approx. 1500 m2 asphalt surface course mastic asphalt, produced in a structured way
approx. 12150 m2 asphalt surface course Produce grit mastic asphalt
approx. 1600 m2 asphalt surface course to produce asphalt concrete
approx. 450 m of dewatering pipelines
approx. 2250 m of infiltration line with seepage pipeline
approx. 750 m3 of pipeline trench making, filling
approx. 130 pcs Install inspection shafts / plastic shafts for seepage pipe
approx. 1100 m Establish drainage pipes DN 150 to DN 400
approx. 4800 m2 of slab covering with concrete slabs (thickness 5/ 8/ 10 cm)
approx. 2600 m2 of natural stone paving pavement, mosaic stone
approx. 1650 m2 of natural stone paving, large paving
Produce approx. 600 m2 of concrete block pavement
approx. 4800 m curb made of natural stone (HB / RB / EF / FB)
approx. 3350 m concrete curb (HB/ TB/ EF)
Road construction - services municipal utilities
approx. 2,550 m demolition/dismantling of dirty water pipes stoneware, GG DN 150 - DN 600
approx. 660 m new construction of sewer DN 200
approx. 843 m New construction of sewer DN 250
approx. 900 m new construction of sewer DN 150
approx. 31 new construction of waste water shafts concrete DN 1000
approx. 550 m new construction of dirty water pressure pipe GGG DN 300
approx. 2000 m demolition/dismantling of rainwater sewer stoneware, concrete DN 150 - DN 1000
approx. 950 m New construction of rainwater sewer DN 150
approx. 362 m New construction of rainwater sewer DN 300
approx. 218 m New construction of rainwater sewer DN 400
approx. 276 m New construction of rainwater sewer DN 500
approx. 477 m New construction of rainwater sewer DN 600
ca. 217 m New construction of rainwater sewer DN 700
approx. 943 m Dismantling of drinking water pipeline GG DN 80 - DN 150
approx. 740 m New construction of drinking water pipeline GGG DN 300
approx. 470 m New construction of drinking water pipeline GGG DN 250
approx. 330 m new construction of drinking water pipeline PE 125
approx. 180 m new construction of drinking water pipeline PE 63
approx. 820 mNeubau Trinkwasserleitung EP 32
approx. 92 pieces of new construction of drinking water house connections
approx. 1076 m Dismantling of gas pipelines steel DN 150 - DN 300
approx. 595 m New construction of gas pipeline PE 355
approx. 371 m New construction of gas pipeline PE 315
approx. 200 m new construction of district heating pipeline KMR 150/280
approx. 102 m new construction of district heating pipeline KMR 125/250
approx. 454 m New construction of district heating pipeline KMR 65/160
approx. 202 m new construction of district heating pipeline KMR 200/400
approx. 2818 m New power line NAYY 4 x 240