The purpose of the contract will be to carry out Civil Engineering, Locksmithing and General Services works.
The overall project linked to this contract is the installation of turbine on the reserved flow of the Rabodanges hydroelectric development (61);
This contract notice concerns lot GC. The IEG HTA and Group lots are the subject of separate contract notices;
The purpose of this contract is the turbine of the flow reserved for the Rabodanges hydroelectric plant and in particular:
- The establishment of general site facilities and accesses,
- Construction of a room, to house the new turbine unit of the reserved flow, watertight up to 115 mNGF-L, with a roof removable or equipped with a hopper with removable hatch and a sound envelope,
- Anchoring and sealing of the mechanical elements for transmitting the forces of the production group (foot valve, tarpaulin, vacuum cleaner, generator, ...) at the level of the factory room,
- Supply and installation of the various locksmith elements (stem, watertight doors, windows, staircase, platform, railings, ladders ...)
- Construction of an outdoor shelter above the 115 mNGF-L hill for capacitors,
- Supply and installation of a new access bridge to the bypass valve for the restitution of the reserved flow and the capacitor cabinet. It is allowed variants on the accesses and location cabinet capacitor to limit the number of access accessory;
The main objectives and constraints of the Market are as follows:
- The implementation of all the mechanical equipment necessary for the production and optimal exploitation of the reserved flow,
- The operation is scheduled between June 2024 and December 2024;
The main characteristics of the project are presented on the few attached plans.
This list is not exhaustive. The total scope will be described in a specification which will be attached to the consultation file.