1. The object of the order is the construction of sanitary sewerage system on the territory of Małkowo and part of the village Żukowo within the streets: Palace, Pogodna, Brzozowa, Spokojna, Dębowa, Lipowa, Słoneczna, Zbożowa, Parkowa, Dworska, Żurawa, Zielona and Posnowa along with a compressed collector with a inclusion in Pępowa in the Peasants' Street. The investment is located in the territory of Zhukovo Municipality.
2. The subject of the order also includes its scope: the construction of sections of connections from the network to the borders of private parcels hereinafter referred to as connections, the construction of a network of compressed sewage system, together with two pumping stations and accompanying infrastructure.
3. Detailed description of the object of the order is specified in the SWZ and the technical documentation.
1. The object of the order is the construction of sanitary sewerage system on the territory of Małkowo and part of the village Żukowo within the streets: Palace, Pogodna, Brzozowa, Spokojna, Dębowa, Lipowa, Słoneczna, Zbożowa, Parkowa, Dworska, Żurawa, Zielona and Posnowa along with a compressed collector with a inclusion in Pępowa in the Peasants' Street. The investment is located in the territory of Zhukovo Municipality.
2. The subject of the contract also includes its scope: the construction of sections of connectors from the network to the borders of private parcels hereinafter referred to as connections, the construction of a network of compressed sewage system, together with two pumping stations and accompanying infrastructure, and in particular:
PRESSED SEWERAGE
1) Piston Pipeline Ø 125 PE — approx. 2450 m,
2) Piston Pipeline Ø 90 PE — approx. 780 m
GRAVITATIONAL SEWERAGE
3) Gravity sewer network Ø250 PVC — approx. 15 m,
4) Gravity sewer network Ø200 PVC SN 8 and SN12 — approximately 8000 m,
5) Sections of gravity sewer Ø160PVC completed with a cap — approx. 1680 m.
6) Wastewater pumping station with landscaping — 2 pcs
WATER SUPPLY CONNECTORS FOR WASTEWATER PUMPING STATIONS
7) Water supply connection Ø90 PE with fittings — approx 17 m
8) Water supply connection Ø40 PE with fittings — approx 64 m
OTHER
9) recreation of the site after the robots to its original state and according to the documentation except for the restoration of bituminous pavement on Palacowa Street. In Palace Street, the entire asphalt will be replaced as part of the Municipal Programme. Instead of bituminous layers, mechanically stabilized broken aggregates must be used.
3. Detailed description of the item of the order can be found in Section III of the SWZ and the technical documentation.