Construction of new pressure pipeline from Haldenbach to Krättenbach in Kernen 71394 - Kernen i. R.
Civil engineering and pipeline works, road construction works - main masses
Abbreviation Number
Pipeline trench and backfill 3,050 m
Druckrohrleitung PE-HD da 315 mm 3.050 m
Leerrohre PE DN 100 9.150 m
Pipe jacking HDD method incl. pressure pipe HD-PE da 315 630 m
Pipe jacking HDD method incl. empty conduit HD-PE da 110 1,900 m
Fertigteilschächte DN 1500, DN 2000, DN 2500 16 St
Asphalttragschicht 750 m2
Asphaltbinderschicht 50 m2
Asphaltdeckschicht 800 m2
Asphalttragdeckschicht 5.500 m2
Gate valves / fittings DN 300 35 St
Edelstahlrohrleitungen DN 150-300 50 m