Description:
St. Elisabeth Krankenhaus Wittlich — restructuring of the maternity unit — technical equipment, plant groups 1, 2, 3, 7 and 8, service phases 1-9 according to §§ 53 et seq. HOAI

At the St. Elisabeth Union Hospital in Bernkastel-Wittlich, the existing maternity unit on the 3rd floor is scheduled for vacancy in the former internist function. This area is particularly suitable for use as a new maternity unit, as proximity and convenient access to the areas of the premature and infant ward as well as the gynaecological clinic can be maintained and the previous maternity unit can continue to operate during the conversion phase.

Total costs (Kgr. 200-600, DIN 276) are currently assumed to be around 2.1 million gross (as of 2019).

It is intended to commission the following services (in stages) with this tender:

Technical equipment, plant groups 1 (wastewater, water, gas plants), 2 (heat supply systems), 3 (ventilation systems), 7 (user-specific plants/(here: fire extinguishing systems and media supply systems) and 8 (building automation), service phases 1 to 9 according to §§ 53 et seq. HOAI.

At the St. Elisabeth Union Hospital in Bernkastel-Wittlich, the existing and very outdated maternity unit on the 3rd floor is scheduled for vacancy in the former internist function. This area is particularly suitable for use as a new maternity unit, as proximity and convenient access to the areas of the premature and infant ward as well as the gynaecological clinic can be maintained and the previous maternity unit can continue to operate during the conversion phase.

According to the approved feasibility study (as of 2017), the planned measure, with usable space of around 369 m², was to be implemented while the hospital was in operation. After submitting the HU

Construction at the end of 2018, the ministry suggested planning a larger area. The laboratory space is also to be relocated. The area to be converted is already vacant.

Total costs (Kgr. 200-600, DIN 276) are currently assumed to be around €2.1 million gross (as of 2019).

The following milestones are planned:

Start of service: mid/end of January 2022,

Completion: quarter I 2024.

The measure shall be awarded the services of technical equipment, system groups 1 (wastewater, water, gas plants), 2 (heat supply systems), 3 (ventilation systems), 7 (user-specific plants/here: fire extinguishing systems and media supply systems) and 8 (building automation) in accordance with §§ 53 et seq. HOAI.

The services are commissioned in stages. First, the service phases 1 to 2 (basic determination and preliminary planning) are commissioned in the 1st commissioning stage in accordance with § 55 HOAI. The service phases 3-9 are called up in stages. There is no legal entitlement to overall commissioning.

Download full details as .pdf
The Buyer:
cusanus trägergesellschaft trier mbH
CPV Code(s):
71300000 - Engineering services
71315000 - Building services