Gerüstbauarbeiten
Brief description of the measure:
Scaffolding work for a new school building, here only 1st construction phase.
Scope of services Main items:
Fssade scaffolding 3.000m², stair tower 4 pcs, scaffolding inside 650m³, canopies 30lfm, console with screed 1.500lfm, dust nets 840m²
Execution times:
- Construction of façade scaffolding: 12.06. - 24.06.2023
- Provision of façade scaffolding expected until 30.12.2023 (duration approx. 6 months)
- Dismantling of façade scaffolding: within 2 weeks after call
- Internal scaffolding, staircase: expected December 2023 and April 2024