VE 04 - civil engineering foundation
The civil engineering measures serve as preparation for the subsequent refurbishment of the existing buildings and the construction of the extension of the mining museum Oelsnitz / Erzgebirge.
These measures include construction pit construction, construction pit containment, drainage and deep foundation of the new building.
Excavation excavation for the extension includes a quantity of approx. 1 860 m
The works in the area of new buildings include the construction of the excavation pit with open drainage. The Baugrubenumschließ between the existing building is made with carrier planks walls including back anchoring (Berlin shoring). The base of the excavation is about 226 m
In the course of construction pit construction, a partial underpinning of the adjacent buildings by means of statically effective jet-blasting bodies is to be ensured. The currently calculated grouting material is approx. 140 m
Deep foundations include the production of tube injection piles according to the static data in different bottom heights. The individual lengths of the pipe injection piles are between 5 m and 11 m, resulting in a total length of approx. 650 m.