Trade 111: Glass façades wood-aluminium
The construction project involves the conversion of an existing former school building, which will be extended in the north by a large head building and in the south by a smaller extension.
All parts of the building will have 4 storeys and no basement.
The existing building is about 52 x 10.5m in size, the northern extension has a floor area of about 425 m2, the southern extension of about 150 m2.
Trade 111 includes the construction of the wood-aluminium façades of both new buildings as mullion and transom facades as well as the exterior doors. The façades are located in the corridor and stairwell areas of the two new buildings and extend over all four floors as well as in the corridor and foyer areas adjacent to the stairwells on the ground floor.
- from week 41 2023 temp. close windows/facades,
- Start of façade construction south 50th week 2023,
- Completion South 27th week 2024,
- Completion north 48th week 2024
- Dates set in construction consultations and / or fixed in an ongoing construction schedule are binding.