LOS08 - Adaptation of roof work stands
Dacharbeitsstand
Dismantling of the steel structure, adaptation work on the steel structure,
Adaptation work on pipe railings, manufacture, delivery and assembly of the
Width changes in aluminium design and its assemblies, manufacture, delivery and assembly of electrical equipment, adaptation of test field, design control in conjunction with catenary switchgear
- Workshop Gorbitz track 5 a+b, 2 x 60 m on both sides with test field
- Workshop Gorbitz track 6 a+b, 2 x 60 m on both sides
Other services
- Plant and assembly planning
- Revision of structural steel construction and structural change of width
- Commissioning and acceptance