Construction work for school buildings | Tenderlake

Construction work for school buildings

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
27 July 2022
Closing Date:
30 August 2022
Location(s):
DEC03 Neunkirchen (DE Germany/DEUTSCHLAND)
Description:
Use-specific systems Laboratory technology

"Renewal of the laboratory technology for the departments of physics and chemistry as part of the fire protection and energetic upgrading as well as the conversion and renovation of all floors of the main building of the Maximilian-Kolbe-Schule in Neunkirchen-Wiebelskirchen, which is sponsored by the Diocese of Trier.

The work will be carried out in 3 construction phases starting 20 working days after commissioning by the client until mid-2025 (end of 3rd construction phase), whereby the assembly of the laboratory technology must be completed at the end of the 2nd construction phase.

The work takes place during the individual construction phases, with the exception of the school holidays, during ongoing school operations.

The laboratory equipment will be completely dismantled and completely rebuilt.

"The Maximilian-Kolbe-Schule was built in the years around 1975 as a reinforced concrete-skeleton construction (TT beam ceilings on the ground floor and upper floors) or reinforced concrete/masonry construction (basement) with non-load-bearing system partitions (so-called "Mechel walls") as interior walls and a suspended mullion-transom façade. The building has 5 floors (UG-3. Og) and a technical floor.Due to age, there are deficits in the building with regard to building services, fire protection, energy balance, etc., which are to be remedied in the course of the renovation.

The sanitary installations are carried out in 3 construction phases and essentially include the following items:

Disassembly:

- Dismantling of HT/PE pipelines DN 40-100 (approx. 280m)

- Dismantling of cast iron pipes DN 40-100 (approx. 400m)

- Dismantling of rainwater harvesting system incl. 6 tanks a 2.000L

- Dismantling washbasins incl. fittings and corner valves (approx. 57 pcs.)

- Disassembly WC (approx. 28 pcs)

- Demonatge urinals (approx. 17 pcs.)

- Demontage TRW-Ltg. DN 15-65 (ca. 320m)

- Dismantling of gas pipeline DN 25-100 (approx. 100m)

Sewage:

- Sewage pipe & rainwater cast DN 50-150 (approx. 650m)

- Grease trap NS2 (1pcs.)

- Backflow closure type 3 DN200 (1 pcs.)

- Temporary rainwater flat roof (later on the outside)

Drinking water:

- Fresh water station 38l/min incl. Hzg. buffer 1.000L (1 pcs.)

- TRW-Ltg. niro geschweisst 12-88,9mm (ca. 1.100m)

- Pre-wall installation elements WC, WT, AG, Urinal, WC Beh.,WT Beh., sink, WM (approx. 80 pcs.)

- WC barrier-free (2 pcs.)

- WT barrier-free incl. fittings (2 pcs.)

- Washbasin WC u classrooms incl. faucet (approx. 48 pcs.)

- Spout basin incl. fitting (approx. 8 pcs.)

- Urinals (9 pcs.)

- Shower (2 pcs.)

- Spülstation TRW-called (10 Pcs.)

- Under-table/surface-top unit 5-10L (5 pcs.)

- Paper dispensers, mirrors, soap dispensers, toilet paper holders, disinfection, waste bins, etc.

- Temporary drinking water connection floors

Gas systems:

- Gas line 60.3-114.3mm (approx. 50m)

- Capsule spring pressure gauge (2 pcs.)

- Connection to existing buildings

- 2-fold paint

Maintenance prices:

- 1st year

- 2nd year

- 3rd year

- 4th year"

Download full details as .pdf
The Buyer:
Bistum Trier
CPV Code(s):
39180000 - Laboratory furniture
45214200 - Construction work for school buildings
51430000 - Installation services of laboratory equipment