Lot 301 - Construction site equipment
The construction site equipment includes traffic safety, protective measures construction fence, container facility, winter construction measures and the construction water system.
Components of the advertised services include:
- Protective measures: 250 m² asphalt protective layer
5 pcs. Protect trees / lanterns
- 346m construction fence
- 4 pcs. construction fence gate 2-wing.
- Container system: total 6 containers, 2-storey (3 x 3), with staircase
- Winter construction heating system: oil heater + blower + hoses; Device with 30kW for
one winter (120 days)
- 93m² excavated soil for construction water
- Construction water: 30m dirty water pipe, 110m drinking water pipe, 2 construction water connection boxes
- Construction doors 4 pcs. 1-leaf, 2 pcs. 2-leaf