The procurement covers the Customer's need for meter fitters to supplement the Customer's department, as well as ongoing meter replacements in addition to the replacements carried out by the Customer's staff + temporary staff.
Background
The 2G network is expected to shut down by the end of 2025. This means that the Customer must replace approximately 14,000 heat meters and approximately 21,000 water meters, all of which are connected to the 2G network. Today, the Customer has a department that performs these changes but needs to be supplemented further until all meters are replaced.
Purpose and goal
The purpose of the procurement is to supplement the Customer's department of meter fitters with an additional approximately three (3) fitters to assist in the daily work and to carry out the meter replacements that the Customer needs to carry out.
The goal is to replace all meters in a qualitative and cost-effective way for the Customer by the end of 2025.
The procurement covers the Customer's need for meter fitters to supplement the Customer's department, as well as ongoing meter replacements in addition to the replacements carried out by the Customer's staff + temporary staff.
Background
The 2G network is expected to shut down by the end of 2025. This means that the Customer must replace approximately 14,000 heat meters and approximately 21,000 water meters, all of which are connected to the 2G network. Today, the Customer has a department that performs these changes but needs to be supplemented further until all meters are replaced.
Purpose goal
The purpose of the procurement is to supplement the Customer's department of meter fitters with an additional approximately three (3) fitters to assist in the daily work and to carry out the meter replacements that the Customer needs to carry out.
The goal is to replace all meters in a qualitative and cost-effective way for the Customer by the end of 2025.
Scope Staffing meter fitters
The procurement includes staffing of meter fitters to the Client's department for meter fitters. The customer estimates the need for approximately three (3) meter fitters to help the Customer replace the heat meters and water meters that need to be replaced by the end of 2025. Other tasks that may be added are new set-up of meters, taking down meters and troubleshooting as well as simple repair work.
At the same time as more meters are changed during the contract period, the Customer estimates that the need for staffing will decrease. The customer's estimate of needs is as follows:
2023-02-01 - 2023-12-31 = Three (3) full-time fitters2024-01-01 - 2024-12-31 = Two (2) full-time fitters2025-01-01 - 2025-12-31 = One (1) full-time fitter
The above data is only an estimate and can differ both up and down. The supplier should be able to deliver the real need.
During the term of the contract, changes may occur based on group decisions, changes in activity and more that may affect the need and volume.