The refurbishment of the Altmühlfranken-Gunzenhausen hospital is being carried out in several phases during ongoing operation. The hospital is divided into 3 main areas, component A, component B and component C in stock. The final stage of the project is to plan all untreated areas in the clinic so that the clinic is completely renovated.
The new medium-voltage switchgear will be set up in relation to the existing MS and will be gradually switched in coordination with the clinic and the energy supplier.
1 pc. Air-isolated measuring field
1 St. Hochführfeld
4 pc. Transformer output fields with load switch
Double floor adapt approx. 15-20 m