The subject of this contract are construction works under the project "Elimination of low emissions in the city of Bytom in the years 2020-2021" – Contract V – Construction of heating networks (2022) – task entitled: "Z6A.20, Z6B.20 Connection to the heating network of the building at Korfantego 8, 8a in Bytom".
The project is co-financed from the Cohesion Fund under the Operational Programme Infrastructure and Environment 2014-2020 Priority axis I Reduction of emissions of the economy, Measure 1.7 Comprehensive elimination of low emissions in the Silesian Voivodeship Sub-measure 1.7.2 Effective distribution of heat and cold
In Silesian Voivodeship.
The scope of construction works includes the construction of a heating connection to the building at Korfantego 8, 8 and in Bytom with a total length of 92.5 m and the construction of 1 heat substation.
The subject of this contract are construction works under the project "Elimination of low emissions in the city of Bytom in the years 2020-2021" – Contract V – Construction of heating networks (2022) – task entitled: "Z6A.20, Z6B.20 Connection to the heating network of the building at Korfantego 8, 8a in Bytom".
The scope of construction works includes the construction of a heating connection to the building at Korfantego 8, 8 and in Bytom with a total length of 92.5 m and the construction of 1 heat substation.
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
1. The Ordering Party shall specify the following deadlines for the implementation of the subject of the contract:
(a) The start of construction works will take place no later than 7 days after the acquisition of the construction site.
(b) The delivery of the material must be reported for receipt after the acquisition of the construction site and after compliance with the conditions laid down in the ZPK.
c) Technological works enabling the supply of heat to customers should be carried out and submitted for acceptance by 15.10.2022 (the scope of technological works is specified in the ZPK Annex 6 to the Agreement).
d) Final works should be carried out and submitted for acceptance by 15.01.2023.
e) Completion of the implementation of the subject of the contract — up to 8 months after the conclusion of the contract
2. The Ordering Party shall set a date for the start of the reception activities and notify the contractor in writing or in e-mail form up to 5 days after receipt of the notification, indicating the place and date of commencement of the reception activities, which will begin up to 14 days after receiving the notification.
3. From the reception activities will be drawn up by the contractor:
(a) Protocol without comments - providing the basis for invoice,
(b) Notes Protocol - not a basis for invoice, not resulting in the accrual of contractual penalties,
(c) negative result protocol - not a basis for invoice, resulting in contractual penalties after the execution deadlines are exceeded.
4. Failure to submit a notification for collection is treated as the inability to collect the subject of the contract or its part, the Ordering Party writes a negative protocol, resulting in the calculation of contractual penalties.