Gurnerschaft Jahn München v. 1887 e. V. /pack of 23 impact wall.
Gurnerschaft Jahn München von 1887 e.V. /VE 23 — impact wall
The object of this invitation to tender shall be the impact wall of the triple sports hall, including access doors, folding doors of the equipment rooms and the corresponding technical openings.
The service includes the manufacture, supply and installation of all parts and elements for substructure and impact wall.
1. Situation construction site
The property of the triple sports hall is located on Weltenburgerstr. 53, in Munich Bogenhausen, it can be accessed directly from Weltenburgerstraße.
Storage and parking spaces are available under the triple sports hall in coordination with the other companies involved in construction in the EC. The triple sports hall itself is located on the 1st floor.
1.1. Construction data:
Bullets: UG, ground floor + 2 OGs
Gross volume: approx. 40 200 m
Gross floor area approx. 7 800 m
Length/width of building: approx. 65/57 m
Eaves height: approx. 13.50 m
Total roof area: 3 050 m
1.2 Construction
The building is erected in reinforced concrete construction.
All walls and ceilings are reinforced concrete.
The triple sports hall is mounted on concrete columns above the parking deck.
The on-site sports floor will already be installed.