The work is divided 7 into lots. Macro lot 1 and macro lot 2 + lot 4 passed in formalized procedure. Other batches (3 - 5 - 6 - 7 - 8) passed in adapted procedure. The work will take place on several levels: 2 in basements & 1 in elevation. The companies will intervene in particular on the RER A slab, the slabs above the future shops and on the SK volume. Considerable vigilance will have to be paid to these elements.
Macro lot 1 and macro lot 2 - demolition/foundations and structural work (formalized procedure)See consultation documents
Lot 3 - escalators, elevators (adapted procedure)See consultation documents
Lot 4 - VRD (formalized procedure)See consultation documents
Lot 5 - lighting (adapted procedure)See consultation documents
Lot 6 - furniture/locksmithing (adapted procedure)See consultation documents
Lot 7 - facade/curtain walls/ clothing (adapted procedure)See consultation documents
Lot 8 - green spaces (adapted procedure)See consultation documents