Maintenance of fire protection and property protection systems as well as emergency and evacuation lighting systems in the buildings of WULS-SGGW in Warsaw for a period of 12 months.
Order divided into parts:
Part I: Maintenance and periodic inspections within 12 months of SSP, smoke exhaust, Gazex, DSO and SUG systems and calibration of gas detectors in the facilities of the Warsaw University of Life Sciences.
Part II: Maintenance and periodic inspections within 12 months of property protection systems in the facilities of the Warsaw University of Life Sciences.
Part III: Maintenance and periodic inspections within 12 months emergency and evacuation lighting installations in the facilities of the Warsaw University of Life Sciences.
5.On-site inspection: a) The contracting authority provides for the obligation of the contractor to carry out an on-site inspection. (written confirmation of the visit required). b) Date and rules of participation in the on-site visit:• The on-site visit should be announced electronically to the following address: dint@sggw.edu.pl.
Maintenance and periodic inspections within 12 months of SSP, smoke exhaust, Gazex, DSO and SUG systems and calibration of gas detectors in the facilities of the Warsaw University of Life Sciences'Maintenance and periodic inspections within 12 months of SSP, smoke exhaust, Gazex, DSO and SUG systems and calibration of gas detectors in the facilities of the Warsaw University of Life Sciences"
• ongoing removal of system faults and defects, replacement of damaged or worn elements,
• periodic checking of the operation of fire alarm systems (including periodic inspections),
• conducting comprehensive checks of the interoperability of SSP systems with other systems installed in WULS-SGGW facilities such as: lifts, SWiN, AC, BMS.
Detailed requirements for the implementation and enforcement of the employment requirement on the basis of an employment relationship are set out in the model contract and annexes to the Agreement.
5. On-site inspection
a) The contracting authority provides for the obligation of the contractor to carry out an on-site inspection. (written confirmation of the visit required).
b) Date and rules of participation in the on-site visit:
• The on-site inspection should be announced electronically to the following address: dint@sggw.edu.pl at least 1 – days in advance (working days from Monday to Friday should be counted). The Contractor in the content of the application/application for participation in the on-site inspection includes:
o Order Name;
o Case No.;
Pursuant to Article 226(1)(18) of the PPL, an offer that has been submitted without a site inspection or without checking the documents necessary to perform the contract available on site at the contracting authority will be rejected.
Maintenance and periodic inspections within 12 months of property protection systems in the facilities of the Warsaw University of Life SciencesMaintenance and periodic inspections within 12 months of property protection systems in the facilities of the Warsaw University of Life Sciences".
• participation in a comprehensive check of the interoperability of the SSP system with other systems installed in WULS-SGGW facilities such as lifts, SWiN, AC, BMS,
• periodic checking of the functioning of access control systems, SWiN,
Detailed requirements for the implementation and enforcement of the employment requirement on the basis of an employment relationship are set out in the model contract and annexes to the Agreement.
5. On-site inspection
a) The contracting authority provides for the obligation of the contractor to carry out an on-site inspection. (written confirmation of the visit required).
b) Date and rules of participation in the on-site visit:
• The on-site inspection should be announced electronically to the following address: dint@sggw.edu.pl at least 1 – days in advance (working days from Monday to Friday should be counted). The Contractor in the content of the application/application for participation in the on-site inspection includes:
o Order Name;
o Case No.;
Pursuant to Article 226(1)(18) of the PPL, an offer that has been submitted without a site inspection or without checking the documents necessary to perform the contract available on site at the contracting authority will be rejected.
Maintenance and periodic inspections within 12 months of emergency and evacuation lighting installation in the buildings of the Warsaw University of Life SciencesMaintenance and periodic inspections within 12 months of emergency and evacuation lighting installations in the buildings of the Warsaw University of Life Sciences".
• participation in a comprehensive check of the interaction of the emergency and evacuation lighting system with other systems installed in WULS-SGGW facilities such as elevators, SWiN, AC, BMS,
• periodically checking the functioning of emergency lighting control systems,
Detailed requirements for the implementation and enforcement of the employment requirement on the basis of an employment relationship are set out in the model contract and annexes to the Agreement.
5. On-site inspection
a) The contracting authority provides for the obligation of the contractor to carry out an on-site inspection. (written confirmation of the visit required).
b) Date and rules of participation in the on-site visit:
• The on-site inspection should be announced electronically to the following address: dint@sggw.edu.pl at least 1 – days in advance (working days from Monday to Friday should be counted). The Contractor in the content of the application/application for participation in the on-site inspection includes:
o Order Name;
o Case No.;
Pursuant to Article 226(1)(18) of the PPL, an offer that has been submitted without a site inspection or without checking the documents necessary to perform the contract available on site at the contracting authority will be rejected.