Renovation of a residential building with 52 residential units and 2 maintenance units (2 units)
Curtain wall (code: VE 306)- substructure, stainless steel, up to approx. a = 210mm: approx. 1,800 m
- mineral wool insulation up to approx. 160 mm: approx. 1,800m
- facade cladding, fibre cement panels: 1,800 m
- Aluminium window sill, exterior: approx. 200 m
- Solar façade: approx. 60 m
- ETICS, walls approx. 710 m
o Incl. facade insulation board up to approx. 120 mm, constructive dowelling, reinforcement layer, finish plaster
o Window sill, outdoor, aluminium: approx. 80 m
o Base construction: approx. 70 m
- ETICS, ceilings approx. 330 m
o Incl. ceiling insulation board up to approx. 80 mm, constructive dowelling, reinforcement layer, finish plaster
- internal insulation basement, ceiling, approx. 80 mm: approx. 410 m
- Internal insulation basement, wall, approx. 80 mm: approx. 30 m
- Balcony construction:
o Steel supports section steel S235, MSH 100-6.3, length approx. 2.75 m: approx. 96 pcs
o Steel supports section steel S235, MSH 100-4, length approx. 2.75 m: approx. 120 pcs.
o Connection angle on ceiling studs starboard -Blanket, l/h/w 34/12/20 cm: approx. 120 pcs.
o Parapet railing: approx. 360 m
o Privacy and wind protection, laminated safety glass, approx. 1.85/1.60 m: approx. 48 hours
- Gazebos:
o Steel columns, profile steel S 235, MSH 101-6-5, length approx. 2.75 m: approx. 81 pcs
o Parapet railings: approx. 185 m
o Glass panes approx. 90/270 cm: approx. 60 pcs.
o Box channel, stainless steel: approx. 210 m
o Bullet bolt, profile steel S235, length approx. 3.20 m: approx. 210 m
- Prefabricated balcony slab, reinforced concrete C35/45 WU, approx. 3.60/1.80 m: approx. 48 hours
Drywall work (including basement partitions) (code: VE 309)- Drywall:
o Metal stud wall, GKB, thickness approx. 100 mm, area approx. 650 m
o Metal stud wall, GKB, thickness approx. 112.5 mm, area approx. 690 m
o Metal stud wall, GKB, thickness approx. 125 mm, area approx. 180 m
o Facing shell, floor-to-ceiling, GKB, thickness up to approx. 75 mm, area approx. 100 m
o Facing shell, height approx. 1.30 m, GKB, depth up to approx. 220 mm, area approx. 100 m
o duct cover, GKB, thickness approx. 75 mm, area approx. 340 m
o GKBI allowance, area approx. 860 m
o Make door openings, approx. 135 pieces, including installation of steel frame frames (on site)
o Inspection flaps, up to approx. 30/30 cm, approx. 180 pcs.
- Drywall ceilings:
o Suspended ceilings, GKB, approx. 270 m
o GKBI allowance, area approx. 30 m
- cellar partitions
o Dividers, height approx. 2.00 m, length approx. 170 m
o allowance doors, approx. 88.5/200 cm, approx. 52 pcs.
Screed work (code: VE 310)- Impact sound insulation, EPS, insulation layer thickness approx. 20 mm, area approx. 3,200 m
- Impact sound insulation, EPS, insulation layer thickness approx. 30 mm, area approx. 320 m
- Ceiling offset, thickness approx. 25 mm, area approx. 190 m
- cement screed, nominal thickness approx. 50 mm, area approx. 3,000 m
- cement screed, nominal thickness approx. 45 mm, area approx. 210 m
- Sloping screed, nominal thickness approx. 45-70 mm, area approx. 320 m
- Mineral-bound fill, thickness approx. 10 mm, area 3,200 m
- incl. setting accelerator