Construction and renovation work.
- Establish pavements around 1,100 m
- Remove wall and facade cladding approx. 290 m
- Attach enamel sheet metal cladding approx. 70 m
- Install tilt window 8 pieces;
- Install T30 doors 10 pieces;
- Create masonry approx. 25 m³;
- Apply wall plaster approx. 445 m
- Renew the flat roof covering approx. 470 m
- Renew F30 drywall ceiling approx. 470 m
- Lay natural stone steps approx. 34 pieces;
- Apply wall and ceiling paint approx. 900 m
- Renew steel corrosion protection approx. 220 m
- Lay porcelain stoneware tiles approx. 250 m
- Lay mosaic wall tiles on jig plaster approx. 150 m
Execution in day work from Monday to Friday from 7 a.m. to 4 p.m. in two construction phases due to passenger traffic for half-sided counter hall closure and partly night work from 9 p.m. to 5 a.m. in interface areas from the 1st and 2nd construction phase.