Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork

Contract Value:
EUR 26M - 26M
Notice Type:
Contract Notice
Published Date:
02 August 2023
Closing Date:
31 August 2023
Location(s):
DE132 Breisgau-Hochschwarzwald (DE Germany/DEUTSCHLAND)
Description:
Remaining planning & erection. of a fibre optic network with house connection management - Müllheim, Auggen, Neuenb

The client is planning to set up an NGA network (FTTB) on part of the municipal area of the municipalities of Müllheim, Auggen and Neuchâtel. The aim is to eliminate any white spots that still exist there.

Lot 1 Müllheim

The client plans to build an NGA network (FTTB) within part of the municipal area of the Verbandsgemeinde of Müllheim. The aim is to eliminate any white spots that are still present there.

The project is to be funded according to the guideline "Funding to support broadband expansion in the Federal Republic of Germany" as well as according to the administrative regulation of the Ministry of the Interior for co-financing the funding from the guideline for the support of broadband expansion in the Federal Republic of Germany (VwV broadband co-financing) and VWV broadband funding. The preliminary funding decision of 21.06.2021 for the project is attached in the attachment preliminary funding decision of 21.06.2021. Overall, investments totalling around EUR 4,425,884.42 net are planned for the expansion of the NGA network (FTTB).

The specifications and specifications of the funding or project promoter regarding the material concept must be observed.

Investments of around EUR 2,622,400.00 net are planned for the backbone.

Planning status Müllheim

The listed route lengths can be reduced or shifted due to co-laying that has been coordinated in the meantime.

Backbone

State Broadband Funding File number: will be submitted later

- New route (paved surface): 8,406 m

- New route (unpaved surface): 4,706 m

- Cable entry into existing conduit: 6,650 m

- Shafts: 19 pcs.

Local network

Federal Broadband Funding e-file number: 832.5/3-2109BW200707

The current planning status corresponds to a design planning based on the existing structural planning. A total of approx. 175FTTB house connections are planned. The project comprises:

- New route (paved surface): 10,052 m

- FTTB distributors (cabinets and/or bays): 17 pieces

- POP prefabricated buildings and/or cabinets: 4 pieces

Furthermore, the eligible drivage based on reserve capacities and the connection of paths of adjacent light grey spots (excluding tunnelling addresses) via the grey spots upgrade are planned. Further strategic-functional connections in the context of the upgrade grey spots are reserved.

The planning status will be communicated accordingly with the request to submit an offer in the next procedural step.

Reference is made in full to the annex to the tender documents.

Lot 2 Auggen

The client is planning to set up an NGA network (FTTB) on part of the municipal area of the Verbandsgemeinde of Auggen. The aim is to eliminate any white spots that still exist there.

The project is to be funded in accordance with the guideline "Funding to support broadband expansion in the Federal Republic of Germany" as well as according to the administrative regulation of the Ministry of the Interior for co-financing the funding from the guideline for the support of broadband expansion in the Federal Republic of Germany (VwV broadband co-financing) and VWV broadband funding. The preliminary funding decision dated 29.03.2021 for the project is attached to the preliminary funding decision dated 29.03.2021. In total, investments totalling around 3,999,709.66 net are planned for the expansion of the NGA network (FTTB).

The specifications and specifications of the funding or project promoter regarding the material concept must be observed.

Investments of around EUR 1,179,400.00 net are planned for the backbone.

Planning status Auggen

The listed route lengths can be reduced or shifted due to co-laying that has been coordinated in the meantime.

Backbone

State Broadband Funding File number: will be submitted later

- New route (paved surface): 3,823 m

- New route (unpaved surface): 2,074 m

- Cable retraction into existing conduit: 497 m

- Shafts: 5 pcs.

Local network

Federal Broadband Funding e-file number: 823.5/3-2009BW200629

The current planning status corresponds to a design planning based on the existing structural planning. A total of approx. 79 FTTB house connections are planned. The project comprises:

- New route (paved surface): 10.739m

- Cable entry into existing conduit: 1,071 m

- FTTB distributors (cabinets and/or shafts): 16 pieces

- POP prefabricated buildings and/or cabinets: 2 pieces

Furthermore, the eligible drivage based on reserve capacities and the connection of paths of adjacent light grey spots (excluding tunnelling addresses) via the grey spots upgrade are planned. Further strategic-functional connections in the context of the upgrade grey spots are reserved.

The planning status will be communicated accordingly with the request to submit an offer in the next procedural step.

Reference is made in full to the annex to the tender documents.

Lot 3 Neuchâtel a. R.

The contracting authority plans to build an NGA network (FTTB) within part of the municipal area of the Verbandsgemeinde of Neuchâtel. The aim is to eliminate any white spots that are still present there.

The project is to be funded according to the guideline "Funding to support broadband expansion in the Federal Republic of Germany" as well as according to the administrative regulation of the Ministry of the Interior for co-financing the funding from the guideline for the support of broadband expansion in the Federal Republic of Germany (VwV broadband co-financing) and VWV broadband funding. The preliminary funding decision of 12.04.2021 for the project is attached in the attachment preliminary funding decision of 12.04.2021. Overall, investments totalling around EUR 11,931,985.15 net are planned for the expansion of the NGA network (FTTB).

The specifications and specifications of the funding or project promoter regarding the material concept must be observed.

Investments of around EUR 2,087,800.00 net are planned for the expansion of the backbone.

Planning status Neuchâtel

The listed route lengths can be reduced or shifted due to co-laying that has been coordinated in the meantime.

Backbone

State Broadband Funding File number: will be submitted later

- New route (paved surface): 4,002 m

- New route (unpaved surface): 6,437 m

- Cable entry into existing conduit: 10,995 m

- Shafts: 15 pcs.

Local network

Federal Broadband Funding e-file number: 832.5/3-2009BW200609

The current planning status corresponds to a design planning based on the existing structural planning. A total of approx. 449 FTTB house connections are planned. The project comprises:

- New route (paved surface): 27,526 m

- New route (unpaved surface): 4,093 m

- Cable entry into existing conduit: 15,667 m

- FTTB distributors (enclosures and/or shafts): 44 pieces

- POP prefabricated buildings and/or cabinets: 6 pieces

Furthermore, the eligible drivage based on reserve capacities and the connection of paths of adjacent light grey spots (excluding tunnelling addresses) via the grey spots upgrade are planned. Further strategic-functional connections in the context of the upgrade grey spots are reserved.

The planning status will be communicated accordingly with the request to submit an offer in the next procedural step.

Reference is made in full to the annex to the tender documents.

Download full details as .pdf
The Buyer:
Zweckverband Breitband Breisgau-Hochschwarzwald
CPV Code(s):
45230000 - Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
45231100 - General construction work for pipelines
45231110 - Pipelaying construction work
71300000 - Engineering services