Rødby Heating Plant will establish a 8.0 MW straw-fired heating plant that will supply district heating to Rødby. This contract includes the supply of electricity, control and machine to a complete straw firing plant incl. design, delivery, assembly and commissioning.
This supply includes the supply of electricity and machinery for a straw-fired heating plant with a thermal output of 8.0 MW. The range includes robotic crane, firing system, boiler, grate, flue gas cleaning, chimney, ash transport and district heating installations as well as electrical and SRO systems. The tendering procedure is a general contract. The supplier thus becomes responsible for all planning, delivery, installation and commissioning.
Building facilities and VAK are offered in parallel in independent tenders. The contract limits are stated in the tender documents.