VE 01: Track and traffic construction, traffic routing during the construction period
Waldstraße between Leutzscher Allee and Primavesistraße
preliminary remarks:
- Construction under full closure for tram operation
- Construction taking into account the existing tree population
General:
- construction site equipment
- Construction site and traffic safety
- Safeguarding evidence
- control checks
- surveying
- ordnance sounding
Traffic management:
- Construction and maintenance of a traffic routing system for the state of construction,
- Establishment of several construction areas, taking into account the use of rescue vehicles and personal rescue in the construction sector
Track construction:
- approx. 1,000 m of double track in the type of cross-sleeper track on a special railway body with track shelves on both sides (provision of rails and sleepers free, construction site is carried out by AG) with slab closure / road construction work
- 4 x rail pull-out devices incl. loading/unloading/transport service from switch and plant construction from Haferkornstraße to the construction site
Fahrleitungsarbeiten:
- approx. 1,000 m renewal of catenary system
- approx. 12 pcs catenary masts, partly as combination masts with lighting and separate lighting masts with production of lighting and cable laying
Traction current:
- Approx. 1,000 m of cable trenches for 2- to 8-speed cable laying in parts with empty conduit laying (cable delivery and cable pulling is carried out by another contractor) with restoration of the ceiling closures in the pavement/street area
- approx. 3 pcs control cabinet
Traffic light system:
- approx. 100 m trenches with piping
- approx. 3 foundations for mast position at three locations
road construction:
- Approx. 1,000 m² bit. Road construction
- approx. 2,700 m² footpath/cycle path