Establishment of telecommunication lines, connection of subscribers
- Funding addresses / buildings: 716 (as of February 2023)
- Connection to property boundary 195 (homes passed)
- Addresses with contract (GNV) 520 (homes connected) to the house.
- Connection Schools [number] 1
- Expected late registration addresses 71 in lot ASB 3
- Distributor primary collocation KoVt / PVt 7
- Power distributor, NVt, [number] 32
- Shafts, [number] 22
-Routes [m] Civil engineering: approx. 33,000 in total, of which are
-->Cable plough distance [m] approx. 9,500 and
--> boreholes [m] approx. 4,000
- House connections [m] civil engineering: approx. 33,150 in total,
- Crossings D-Bahn- 0
- Crossings BAB 14- 0
- Water crossings [number] 24
- Laying of protective pipes [km] approx. 13.1
- Laying of pipe assemblies [km] approx. 114
- Cable pull and assembly [km] approx. 173