Construction of the outdoor facilities as part of the thorough renovation of the town hall in Groß -zimmer.
- Pick up concrete pavement: 100 m
- Deliver base layer of mineral mix 0/32 mm: 230 t,
- Delivery and installation of facade channels: 17 m,
- Supply discharge pipes DN 100: 40 m,
- Supply yard inlet: 2 pieces,
- Lay stored concrete pavement: 120 m
- Delivery and laying of concrete paving: 150 m
- supply and manufacture single-row pavement edging: 26 m,
- Deliver and lay concrete slabs as splash protection: 25 m
- Delivery and installation of guide stones for the blind: 24 pieces,
- Install stored concrete block steps: 12 pcs.,
- Delivery and installation of concrete block steps: 7 pieces,
- Install concrete corner stones: 18 m,
- Deliver and install steel railings: 14 m,
- Deliver and plant solitary trees: 4 pcs.,
- Supply and plant trees and shrubs: 85 m
- maintenance work and watering for 2 years,
- Reinstall stored benches, rubbish bins, bicycle hangers,
- Delivery and installation of walk-off mats, planters, including all necessary ancillary services.