Federal Foreign Office
Renovation and extension Kurstraße 33
prez. constructive demolition and demolition work - DIN 18459
Constructive demolition of non-pollutant components
after pollutant remediation, in the run-up to a conversion measure
Quantity or scope of order
Total quantity or scope:
- demolition of a single-storey gym, floor area 470 m², height 8m;
reinforced concrete, steel beams, masonry
- demolition of a single-storey stem made of precast reinforced concrete elements, 35x4m, height 6 m, approximately one-third integrated into soil,
with two side staircases, roof area as terrace with steel parapet and pre-hung concrete slabs
- disposal of 1100 t concrete, 204 t masonry brick, 11 t steel
Start and end of order execution
Start execution 02/2022
End of execution 09/2022