Construction of all 110 kV components in the open-air plant including civil engineering, foundations and portals for the new 110 kV SF. Construction of a new substation. Erection of curb surrounds as well as sidewalks.
Construction of all 110 kV components in the open-air plant including civil engineering, foundations and portals for the new 110 kV SF. Construction of a new substation. Erection of curb surrounds as well as sidewalks.
Delivery and installation of a 5-span 24 kV SF6 gas insulated switchgear, single busbar, with vacuum switch, max. rated voltage 24 kV, with a nominal current of 2000 A and nominal short-term current 25 kA (3s).
Delivery, installation and commissioning support of primary and secondary equipment to be delivered or provided, such as control cabinets, components of the open-air system, the 20/110 kV transformer of the earth fault compensation systems and the system lighting.
Installation and commissioning support of the digital protection control units.
Partial expansion of new 20 kV cable routes and cable pull shafts/pipe system for secondary cabling from the building to and within the 110 kV open-air system.
Delivery and installation of a 5-field e-coil switchgear including the primary and secondary cabling.
Cable routing, assembly and connection of 20 kV cables provided on site.
Documentation of the complete primary and secondary technology.
All project management and documents must be prepared in German.
All versions according to relevant IEC, EN or DIN standards, as well as applicable VDE regulations and VDEW recommendations according to the latest state of the art.