Overall dimensions: New construction (new construction component I) and restructuring (new construction / demolition component II and component III) of the previous comprehensive school Senefelder School Treuchtlingen in several construction phases with ongoing school operations.
As part of the restructuring, the three school types of middle school, junior high school and high school will be combined in one building under the roof of the integrated and differentiated comprehensive school and equipped with flexible rooms and learning areas.
Because the dimensions. Several construction phases are planned to take place during ongoing school operations:
- Preliminary run: partial cancel Existing building "Mensa" for new building measure BT I;
- 1st construction phase: three-storey new building BT I school specialist classes on the eastern property:
- 2nd construction phase: Abbr. Existing specialist classes;
- new building of sports hall BT II;
- 3rd construction phase: Abbr. Existing sports hall;
- new three-storey school BT III:
Classes / administration of the teachers' room - follow-up: demolition of existing classroom wing and lunchtime supervision
Manufacture of outdoor facilities
Approx. 230 m2 wall and floor composite waterproofing in C - very high W3-1 approx. 210 m2 wall & floor composite seal in A - high W2-1 approx. 600 m2 wall tiles in 30x10 cm, approx. 200m2 floor tiles in 10x10 cm