Electrical Engineering for the 1st BA
Brief description of the measure:
In addition to the existing main building, a 3-storey new building for a primary school is to be built on the site of IGS Lindenfeld. The construction project will be carried out in 2 construction phases. The benefit described here concerns the 1.BA. The building will be constructed in solid construction.
For further descriptions, see specifications
Start of work: 21.08.2023
Interim periods:
Rohinstallation 21.08.2023 - 10.11.2023
Installation 13.11.2023 - 26.01.2024
Final assembly August - September 2024
Acceptances / Commissioning : August - September 2024
Completion: 01.10.2024