Heating installations: In the course of the general renovation and expansion of the Goldbach primary and secondary school, construction phases 1.3 and 1.4 are to be carried out. In BA 1.3 mainly work is to be carried out in existing buildings, in BA 1.4 it is the new construction of the extension building in wood/concrete hybrid construction.
BA 1.3 Work in the Existing Technology, MZR-Aula:
1 heating distributor, 6 outlets, incl. pumps, fittings,
50 fittings DN 15-65,
8 pcs radiator,
1,050 m of pipes made of steel and plastic DN15-65,
BA 1.4 Erweiterungsneubau:
1 heating distributor, 5 outlets, incl. pumps, fittings,
60 fittings DN 15-65,
10 radiators,
1266 m² underfloor heating,
1,100 m of steel and plastic pipelines, DN15-65,