Doemens e. V. intends to build a new training and further education facility with administration. The planned building project is a facility for inter-company vocational training. The objective of the planning is a compact three-story building on Lohenstrasse.
The current tender relates to the execution of the locksmith and steel construction work.
Core quantities (approx.):
Steel structures bridge escape balconies 2 990 kg, steel structures cantilevered escape stairs 1 590 kg, steel structures escape stairs 6 740 kg, gratings 120 pieces, steel structure inner stairs 3 680 kg, steel stair rails 6 pieces, steel strings 1 520 kg, steel structure for ventilation devices 2 160 kg, Steel structure for empties / soundproofing wall 2 590 kg. Estimated execution dates:
Start: August 2020; Completion: February 2021; Installation of inner railing: 1.8.-31.10.2020; Installation of bridges: 1.8.-30.9.2020; Assembly of escape stairs: 1.10.-30.11.2020; Assembly of empties warehouse: 1.12.2020-31.1.2021; Various remaining work: until January 31, 2021.
Doemens e. V. intends to build a new training and further education facility with administration. The planned building project is a facility for inter-company vocational training. The objective of the planning is a compact three-story building on Lohenstrasse.
The current tender relates to the execution of the locksmith and steel construction work.
Core quantities (approx.):
Steel structures bridge escape balconies 2 990 kg, steel structures cantilevered escape stairs 1 590 kg, steel structures escape stairs 6 740 kg, gratings 120 pieces, steel structure inner stairs 3 680 kg, steel stair rails 6 pieces, steel strings 1 520 kg, steel structure for ventilation devices 2 160 kg, Steel structure for empties / soundproofing wall 2 590 kg. Estimated execution dates: