The new building of the sports hall will be built on the area of the previous sports field at the school between the school building and Waldschmidtstraße.
The building is predominantly a reinforced concrete structure with EIFS. The roof of the sports hall is hipped. The
Roof construction is designed as an explosive device with wooden trusses and steel tension struts. Buildings for
changing rooms, plumbing, technology, equipment and gallery with a green flat roof.
Exterior building dimensions: approx. 38 x 45 m
Building height: approx. 14 m
masses:
365 m2 Linoleumbodenbelag
115 m2 Vinylbodenbelag
455 m Skirting
Events:
Ausführungszeitraum: 01.03.2023 – 18.07.2023
W+M planning: 01.03.2023 – 31.03.2023
Linoleum approx. 440 m2 with skirting boards: 27.06.2023 – 18.07.2023
Additional CPV codes
45432130-4 Flooring work