Due to constantly increasing needs, requirements and number of pupils, there is a
of the city of Spremberg/Grodk required the school/educational location of the BOS at the
Wirthstraße 1 in Spremberg, to be expanded or adapted. The current 3-speed
Reputation-oriented secondary school for grades 7-10, should be at least 4 classes
(better 5-speed). Decision G/IV/19/0172-2
phase commissioned the general feasibility and economic feasibility study.
Ben. Furthermore, possible locations were investigated and 3 variants were identified.
. By decision G/VII/21/0051, the decision was made in favour of the location on Wirthstraße.
and by the city councillors with a decision in principle G/VII/21/0120
from 16.06.2021 to variant 3. As a result, a 4-speed expansion
The construction of the building with a 2-field sports hall will be built, as well as the associated outdoor facilities.
and necessary floor space. Parts of the existing building are to be renovated and
can be used for other purposes. The listed sports hall is to be used for
canteen or venue for meetings. According to the current
School requirements planning and the associated number of pupils is even more personal.
It can be assumed that there will be a 5-speed, which will be used in the listed building
Inventory should be mapped variably.
In order to be able to implement variant 3 in its entirety, the necessary
plots of land are acquired, the areas of which are cleared in advance and the existing
Buildings have to be dismantled.
The city administration of Spremberg, Department of Planning and Building, writes object plan-
for the construction of the BOS education campus in Spremberg.
In particular, services (basic services and special services) are put out to tender
(e.g.) for the HOAI service descriptions in the currently valid version:
- Project planning for buildings and interiors
as well as special services, namely:
- Wirtschaftlichkeitsuntersuchungen
- Updating the space program (from 4-speed to 5-speed)
- Participation in the procurement of loans and subsidies
- Preparation of special presentation aids, which are necessary for clarification in advance.
Throwing process is not necessary, for example
- Perspective representations/visualizations
- Colour and material collages
and additional services, namely:
- Planning of specialist room equipment
The subject of the negotiated procedure is a property planner contract that is to be concluded for the following HOAI service profiles:
* Object planning building
* additional and special services, to the extent described in the tender documents.
Once the contract is awarded, a property planner contract is concluded with a bidder. The order is placed in stages.
planning task
Almost completely detached from the traditional school building, but still in a
strong urban connection to each other, is a modern and future-oriented
high school. The planning task to be carried out consists mainly of
the extension of a 4-class secondary school with a new building attached to the new building.
closed or integrated 2-field sports hall. The aim is to develop new school building concepts,
for an open learning landscape and under the theme of "lifelong learning", in which
Incorporate planning. Private land will be used for the new BOS building.
long of the Friedrichstraße and the existing buildings were demolished. So-
The new school building closes the gap in urban development. The inventory
school building should be integrated into the overall concept of the BOS and education campus in the best possible way.
taking into account functional and spatial structural possibilities of use
can be grappled. Furthermore, the connection between the existing building and the new building, whether directly
or indirectly (schoolyard), using Wirthstraße, an essential
part of the planning task. The original use of the existing sports
The hall is to give way to flexible multi-purpose use. These are the currently valid
to comply with structural and building regulations