Ålesund kommune [Ålesund municipality] hereby invites tenderers to participate in a competition for new construction of Kolvikbakken Lower Secondary School.
Contract form: interaction contract in phase 1 with transition to a turnkey contract in phase 2 (the implementation phase).
The contract includes: the assignment has 2 parts, first the preliminary project for which there will be interaction, then further implementation if the project is within the municipality's functional wants and economic limits.
Phase 1: The draft and preliminary project phase: there is a complete draft project from XPRO AS. In the next phase, the preliminary project is in interaction between the turnkey contractors interaction group and the builder.
Phase 2: The implementation phase: Execution of Kolvikbakken Lower Secondary School, new construction.
The Contracting Authority has chosen an interaction contract for the implementation of the project in Part 1 'the draft and preliminary project phase’, and this means that the character and execution of the project can be changes underway.
Ålesund kommune [Ålesund municipality] hereby invites tenderers to participate in a competition for new construction of Kolvikbakken Lower Secondary School.
Contract form: interaction contract in phase 1 with transition to a turnkey contract in phase 2 (the implementation phase).
The contract includes: the assignment has 2 parts, first the preliminary project for which there will be interaction, then further implementation if the project is within the municipality's functional wants and economic limits.
Phase 1: The draft and preliminary project phase: there is a complete draft project from XPRO AS. In the next phase, the preliminary project is in interaction between the turnkey contractors interaction group and the builder.
Phase 2: The implementation phase: execution of Kolvikbakken Lower Secondary School, new construction.
The Contracting Authority has chosen an interaction contract for the implementation of the project in part 1 'the draft and preliminary project phase’, and this means that the character and execution of the project can be changed underway.