The purpose of the Global Operation is to replace and strengthen the drinking water transfer pipeline between Bouyouni and Mamoudzou in order to increase its capacity and reliability. This consultation concerns the replacement and reinforcement of the pipeline of sections 3 and 5. It is the subject of an allotment in 4 work packages
mayotte - commune of Bandraboua (97650) - Village of Mitséniit concerns the construction of the AEP cast iron DN 500 network from the upstream connection point (limit T2/T3) to the junction point with lot 2
lot 2 : Mayotte - commune of Bandraboua (97650) - village of MitséniLot 2 is the downstream part of Section 3
mayotte - commune of Koungou (97690) - Village of LongoniLot 3 constitutes the pipe part of section 5, upstream and downstream of the crossing structure
mayotte - commune of Koungou (97690) - Village of LongoniLot 4 concerns the construction of a metal frame footbridge and its foundation and the laying of the DN 500 pipe section on the footbridge