Pollutant remediation and demolition
total
Execution start: 22.02.2022
Execution end: 21.09.2022
“* Dates for performing the main performance on the construction site:
Start of service 22.02.2022; performance end 21.08.2022
* Description of the procurement:
Demolition of a freestanding building consisting of an indoor ship and two overhead buildings in Rostock. Gross volume approx. 42,175 m³. Footprint 5.040m². Building height up to 13.3m above ground. Demolition outdoor facilities and surface fixing. clearing out, gutting, pollutant removal. Demolition work using asbestos, KMF and PAH. Disposal of all demolition waste including documentation.traffic safety measures. Delivering and setting up a species conservation tower.”
Appointments:
demolition rain gutters and roof plates until 15/03/2022, demolition roof overhangs and canopy until 15/04/2022; construction of species protection tower until 30/04/2022